Case Study · Retail · Cybersecurity
The cyber
backlog
A scattered cyber-security backlog pulled into one governed portfolio — 24 workstreams funded, owned and scheduled, run to a clean handover in June 2026.
Senior Programme Manager, Cybersecurity Transformation & Portfolio Delivery • Jan 2024 — Jun 2026 • 18 control domains across 360+ stores • reporting to the CITO and CISO
Why it mattered
Woolworths was fixing its cyber risk in pieces. Dozens of disconnected remediation tasks sat with individual engineers across Cyber and Infrastructure, with no single view of what was done, owned or overdue. Through 2024, internal assurance and independent assessments turned that noise into a defined set of findings — across identity, legacy platforms, network segmentation and data access — each with a risk rating and a priority. Those findings became the portfolio’s first workstreams.
The mandate was to make them move as one: fund, own and schedule every workstream, run the governance that held the line, and tell the CITO and CISO the truth each month about what was — and was not — getting done. A second mandate ran alongside it: the enterprise compliance programme, certified by its March 2025 deadline, recorded separately in the portfolio of evidence.
The work
Deliver security uplift on an estate still being modernised, using engineers already fully committed to running it.
Legacy platforms sat inside critical applications, one shared engineering team carried everything, and dependencies chained the whole portfolio — service-account hardening waited on MFA, which waited on directory remediation, which waited on server lifecycle.
One governed programme: one tracker, one monthly decision forum, one honest status.
Weekly one-on-ones with every technical lead replaced status-by-email. A monthly Steercom with the CITO and CISO took the hard calls — a scope freeze, a Red rating, descoping — on evidence. Every completed control was signed off into a named BAU team.
Ten controls delivered and owned, the remaining work named and dated, and a structured handover on 30 June 2026.
Legacy head-office servers dropped from 1,000+ to under 200. MFA and privileged access were remediated and signed off. A three-year record of every workstream’s status and decisions made the handover clean.
How it was run
Portfolio roadmap tracker
One register of all 24 workstreams — control domain, risk rating, priority, status, due date, leadership owner, technical lead. Updated weekly.
One-on-one working sessions
Weekly sessions with every technical lead to unblock, re-plan and capture true status — replacing status-by-email.
Portfolio Steercom
Monthly decision forum with the CITO, CISO and leadership owners: RAG, financials, scope changes, descoping, forward-year positioning.
Honest health reporting
Portfolio health reported to IT leadership monthly — and moved to Red when the evidence said so.
Financial reconciliation
Budget, actuals, contingency and monthly burn tracked against the business case; reconciled with Finance before handover.
Change control & closeout
Every delivered control logged as a formal change with RACI sign-off; a standard closeout report per completed workstream, naming its BAU owner.
The record
- Store domain controllers
- Upgraded across 360+ stores
- Store endpoints
- 3,600+ replaced or re-imaged onto a CIS benchmark-hardened baseline
- Legacy head-office servers
- Down from 1,000+ to under 200
- Identity & privileged access
- MFA expansion, service-account hardening, vault mobilisation, access tiering
- Directory recovery
- Forest recovery built and tested — three-day recovery
- Cloud security
- Foundational controls across two cloud platforms, cloud privileged access
- Network defence
- Segmentation, firewall optimisation, WAF live, geo-blocking across the estate
- SOC & detection
- Managed SOC onboarding, log ingestion, third-party risk monitoring
- Assurance
- Pen-test cycles, red/purple-team activity, executive tabletop exercises
Decisions that shaped it
Scope freeze. No new workstream mobilised until in-flight work concluded. Capacity concentrated on finishing — and the freeze held all the way to handover.
Zero Trust reframed. Moved from roadmap item to a leadership working group: a strategy to define, not yet a project to run. No premature implementation spend.
Red reported as Red. A dependent tooling project moved to Red when its funding gap and timeline slip were confirmed. Honest health, escalated funding route.
Buy nothing you don’t need. A network access control requirement was met through an existing capability — one fewer tool to buy and run, requirement still met.
The three principles
“Karli took on a task that many had previously considered impossible, yet she not only delivered successfully but did so on time and within budget.”
Edwin Saulse · Lead Architect on the portfolio · Certified in Cybersecurity, CISSP, CCSP · February 2026
Individuals at the client are referred to by role only. Figures are the programme tracker’s own records at the dates stated, not independently audited. Budgets and vendor names are deliberately withheld. Full evidence register held in the KTH-Tech portfolio of evidence.