Case Study · Retail · Networks
The VDOM
collapse
Eight live firewall domains migrated phase by phase, then a single 29-hour window to collapse the legacy network — zero escalations, not one trading outage.
Apr 2023 — Apr 2025 • part of the Massmart national infrastructure programme • firewall estate of eight virtual domains • PCI DSS and Walmart group segmentation
Why it mattered
The legacy network core terminated in the primary datacentre that had to be exited — so the network could not simply be copied across. The firewall estate ran as eight separate virtual domains joined by transparent Layer 3 routing: a legacy constraint that group security standards and PCI DSS segmentation could not live with. Carrying it into the new facilities would have been faster, and wrong.
At the same time, every retail and distribution site in the country depended on connectivity that was being rebuilt underneath it — fibre, LTE and microwave rollouts, WAN integration and international group links. A cutover window in one region was trading time in another. The network had to collapse, rationalise and re-segment while everything above it kept running.
The work
Collapse and redesign a live eight-domain firewall estate carrying PCI-scoped traffic, without a single trading outage.
Applications, SAP, IPSec tunnels, third-party integrations and international links all ran through the legacy core. Moving one without the others broke the chain — and no window existed in which everything could move at once.
Phase by domain: stage, separate, migrate, validate — and only then collapse the legacy environment.
Each virtual domain carried its own firewall rules, IPSec requirements, routing changes, validation plan, cutover window and rollback. Segmentation and PCI scope separation were designed into each phase and evidenced before cutover, never retrofitted.
A seamless multi-domain network aligned to group security standards, with the legacy environments collapsed behind it.
Inter-domain routing redesigned in flight, national connectivity delivered with minimal operational disruption, and two complete site LAN refreshes handed over — assessment to cabling to testing.
How it was run
Domain-by-domain staging
Each of the eight virtual domains analysed, staged and separated before its migration — never a big-bang cutover across live traffic.
Routing redesign in flight
Inter-domain connectivity moved from transparent Layer 3 routing to a seamless multi-domain design during the migration — the one moment the network had full attention and funding.
Per-wave security gates
Firewall rules, segmentation, VPN and PCI DSS scope separation evidenced before every cutover, aligned to Walmart group requirements.
IPSec & third-party coordination
Tunnels, third-party integrations and international group links re-terminated wave by wave so nothing was stranded in a facility being exited.
National connectivity rollout
Fibre, LTE and microwave deployments across retail and distribution sites, with multi-vendor scheduling and regional cutover windows respecting trading hours.
Collapse last, not first
Legacy network environments were collapsed only after their traffic was proven on the new design — rollback stayed real until it was no longer needed.
The record
- The collapse
- 29-hour change window; two weeks of hypercare, zero escalations.
- Firewall estate
- Eight virtual domains migrated through a phased transition.
- Inter-domain routing
- Redesigned from transparent Layer 3 to a seamless multi-domain network.
- Legacy environments
- Collapsed after migration — traffic proven first.
- National connectivity
- Fibre, LTE and microwave across retail and distribution sites.
- WAN & group links
- WAN integration and international group connectivity delivered.
- Segmentation & PCI
- Scope separation, access control and firewall rules evidenced per wave.
- Site LAN refreshes
- Two sites end to end — assessment, design, cabling, testing, handover.
- Change recovery
- No network change took longer than an hour to fix.
Decisions that shaped it
Phased, never big-bang. Eight live domains with PCI scope could not move in one window — each got its own staging, validation and rollback.
Redesign in flight, not after. Preserving the legacy routing would have preserved the problem. The migration itself was the redesign window.
Security as a design input. Segmentation evidenced before each cutover cost less than a remediation programme after the move — and avoided a second round of change on a live estate.
Respect the trading map. Regional cutover windows were planned around national trading hours — one region’s quiet window is another’s peak.
The three principles
“Karli’s expertise, leadership, and professionalism were instrumental in the successful execution of our projects. Her proactive problem-solving approach, vendor management, risk mitigation and ability to remain composed under pressure ensured projects remained on track and within budget.”
Benjy Singh · Group Tech — Infrastructure & Networks, Senior Manager II, Massmart · formal reference · February 2025
Part of the Massmart national infrastructure programme (Apr 2023 — Apr 2025). Client individuals are referred to by role; the firewall vendor and network products are described by category, not by name. No contract values or budgets are disclosed. Figures are the programme’s own recorded positions, not independently audited.