Case Study · Retail & Wholesale · Infrastructure

Keep the tills
trading

Five datacentres consolidated into two colocation sites and the legacy core collapsed — while the tills kept trading at national retail and distribution sites.

Apr 2023 — Apr 2025 • Senior Infrastructure Project Manager • 200+ stakeholders • Walmart group standards in every wave

5→2
Legacy datacentres consolidated into two colocation sites
8
Firewall virtual domains migrated without a trading outage
100%
Backup media-agent capacity remediation completed

Why it mattered

Massmart’s estate had accumulated five datacentres, a legacy network core terminating in the primary one, SAP on ageing proprietary hardware, and an application portfolio that had never been rationalised. The group had to exit the legacy facilities and land its enterprise workloads in modern colocation — without interrupting trading at national retail and distribution sites.

Three forces set the mandate: the primary datacentre had to be exited, making every dependent workload, integration and network path a dated deliverable; Walmart group standards and PCI DSS demanded segmentation the legacy network could not provide cleanly; and duplicated applications and unsupported platforms were absorbing the capacity and budget the modernisation needed.

The work

The challenge

Move live, interdependent systems between datacentres while stores and distribution centres kept trading.

Applications, SAP, firewalls, IPSec tunnels, third-party integrations and group links all terminated in the legacy core — move one without the others and the chain broke. A cutover window in one region was trading time in another, and 200+ stakeholders had to move together.

The approach

One integrated plan, with migration waves as the unit of delivery.

Every application, network path and security control moved together in dependency-built waves, each with its own firewall and IPSec changes, validation, cutover window and rollback — so nothing was left stranded in a facility being exited.

The outcome

Five datacentres consolidated into two, the legacy core collapsed, scope closed and handed over in April 2025.

SAP re-platformed into colocation, the virtualisation platform rebuilt, backup capacity remediated to 100%, and PCI scope separation delivered to Walmart group standard — with minimal operational disruption.

How it was run

Integrated programme plan

One critical path across connectivity, datacentre, SAP, firewall, platform and security workstreams, with cross-stream dependencies made explicit.

Discovery before design

Ownership, dependencies, utilisation, licensing and supportability per facility — feeding retain, retire, re-platform or consolidate decisions.

Migration-wave sequencing

Workloads grouped by dependency into waves, each carrying its firewall and IPSec requirements, routing changes, validation plan, cutover window and rollback.

Security-by-design gates

Firewall rules, segmentation, VPN and PCI DSS scope separation designed into each wave and evidenced before cutover, to Walmart group requirements.

Vendor & engineering coordination

Multi-vendor scheduling for connectivity, hardware, colocation and platform work; technical readiness confirmed before every cutover.

Service transition per wave

Operational readiness, runbooks and support handover as conditions of each cutover — so delivery closed into BAU, not a project backlog.

The record

Datacentre footprint
Five legacy facilities consolidated into two colocation sites — Johannesburg and Cape Town
Primary datacentre exit
Phased migration waves with a 170-member cross-functional team
Firewall estate
Eight virtual domains migrated; legacy environments collapsed
National connectivity
Fibre, LTE, microwave and WAN across retail and distribution sites — minimal disruption
SAP re-platforming
AIX and HANA workloads moved into colocation
Virtualisation platform
Rebuilt on the current major version
Backup capacity
Media-agent capacity remediation at 100%
PCI scope separation
Delivered and aligned to Walmart group controls
Legacy estate
Obsolete servers retired under change control; a decision per application
Cape Town resilience
Active/passive delivered; active/active at 85% at the last snapshot

Decisions that shaped it

2023

Two colocation sites, not five replacements. Johannesburg and Cape Town gave resilience, connectivity and group-standard security without five estates to run.

2023

A phased domain transition, not one cutover. Eight domains carrying live traffic and PCI scope were staged, separated and migrated one by one — legacy collapsed after, not before.

2024

Redesign the network in flight. Carrying transparent Layer 3 routing into the new facilities would have preserved the problem; the target became a seamless multi-domain design.

2024

Resilience in two steps. Active/passive in Cape Town was delivered and proven early; active/active followed once the migrated estate was in place.

The three principles

Sequence is the product. Discover before you move. Security is a design input to every wave.
“Karli demonstrated exceptional leadership, organisational and project management skills throughout the project lifecycle. She coordinated a seamless transition of multiple data centres with minimal downtime and created a collaborative environment that enabled the team to achieve its goals on schedule.”

Shane Boulle · Group Information Security, Solution Architect · Massmart · January 2025

Client individuals are referred to by role. The colocation provider, firewall vendor and platform products are described by category, not by name. No contract values or budgets are disclosed. Figures are the programme’s own recorded positions at the dates stated, not independently audited. Full evidence register held in the KTH-Tech portfolio of evidence.