Case Study · Resilience · Disaster Recovery

Recover in order

Three platforms.One architecture.Ready to test.
ClientMASSMARTMassmart — DR architecture2023–2025

Massmart (retail & distribution, South Africa) · Senior Infrastructure Project Manager (independent contract) · within 2023–2025 · disaster-recovery architecture for the consolidated estate across HPE, Nutanix and VMware platforms · recorded position: delivered to testing readiness.

3 platforms
HPE · Nutanix · VMware — one architecture
Testing-ready
Design, runbooks and objectives handed over
2 sites
Recovery across both colocation sites

Why it mattered

Consolidating into two colocation sites gave the estate something its five legacy facilities had never offered cleanly — a second site to recover into. Foundation-service redundancy made the base resilient; the disaster-recovery architecture extended that to the business workloads, so that if one site were lost, the applications that run stores and distribution could be recovered at the other in a known order, within known times.

The estate ran on three platform families — HPE hardware, Nutanix hyper-converged infrastructure and the VMware virtualisation platform — each of which replicates and recovers differently. One recovery architecture had to span all three, define which workloads recovered first, document the network and storage dependencies each recovery relied on, set recovery-time and recovery-point objectives per workload tier, and produce the runbooks operations would execute in an actual event. The mandate was delivery of that architecture and its artefacts to the point of testing readiness.

01 The Challenge

Three platforms, three recovery models — replication and failover work differently on HPE, Nutanix and VMware, and one architecture had to accommodate all three without three separate DR programmes.

Workload priorities are business decisions — which systems recover first, and how long each may be down, had to be decided by the business owners who would feel the outage, not assumed by infrastructure.

02 The Approach

Built from the business outward — workload priorities and objectives agreed first, dependencies mapped against them, then the platform-specific replication and recovery designs and the runbooks that execute them.

A workload cannot recover before the network, storage, identity and integrations it needs, so mapping those dependencies was the core of the design.

03 The Outcome

A disaster-recovery architecture spanning HPE, Nutanix and VMware across the two colocation sites — with workload priorities, recovery objectives, dependency maps and runbooks — delivered to testing readiness and handed to the client.

Whether the client tested the architecture afterwards is not known and is not claimed.


How it was run

Workload priorities & objectives

Workloads tiered by business criticality, with recovery-time and recovery-point objectives agreed per tier with business owners.

Dependency mapping

Network, storage, identity and integration dependencies documented per workload and per tier.

Recovery architecture

Replication and failover design across HPE, Nutanix and VMware between the two colocation sites.

Runbooks

Step-by-step recovery procedures per tier and platform, written for operations to execute.

Testing readiness

Test approach, scenarios and success criteria defined; architecture and runbooks handed over ready to test.


The record

PrioritiesWorkloads tiered and objectives agreed with business owners
DependenciesNetwork, storage, identity and integrations mapped per tier
ArchitectureOne design across HPE, Nutanix and VMware, two sites
RunbooksPer-tier, per-platform procedures for operations
ReadinessTest approach and criteria defined; handed over ready to test

Decisions that shaped it

2023–2025

Start from the business, not the platform. Priorities and objectives agreed with owners made the technical design a means to an agreed end.

2023–2025

Dependencies are the recovery order. The dependency map decided what the runbooks had to do first.

2023–2025

One architecture, three implementations. One set of tiers and objectives, implemented per platform, avoided three uncoordinated DR efforts.

2023–2025

Say “testing readiness” when that is the position. The record is honest that the test was not in scope.

The three principles

Start from the business. Dependencies set the order. Runbooks are the deliverable.
Start a project → All case studies

The client is Massmart; the engagement was an independent contract within 2023–2025. The recorded position is delivery of the disaster-recovery architecture, runbooks and objectives to testing readiness; no disaster-recovery test is recorded or claimed as part of this engagement. Colocation sites are referred to generically and individuals by role. HPE, Nutanix and VMware are named as the platform families of the consolidated estate. Full evidence register held in the KTH-Tech portfolio of evidence.