Retail · Disaster Recovery
Before the
bad day
A second site. Proven in steps. Ready before it was needed.
Apr 2023 — Apr 2025 • part of the Massmart national infrastructure programme • Cape Town colocation as the group’s recovery site • recovery architecture, replication, runbooks and recovery objectives
Why it mattered
Consolidating five datacentres into two does something uncomfortable: it concentrates risk. When the group’s enterprise workloads land in one primary facility, the second site stops being a nice-to-have — it has to be able to carry the business on the day the primary cannot. And that capability had to be built while the estate was still mid-migration, not bolted on afterwards.
The quiet truth underneath every DR design is the backup estate. Recovery objectives mean nothing if the backup infrastructure cannot physically move the data in time. So the programme treated backup capacity, catalogue hygiene and replication as load-bearing deliverables, not housekeeping — and only claimed readiness the record could support.
The work
Build a recovery site for an estate that was itself moving — priorities, dependencies and platforms changing wave by wave.
Workload priorities and dependencies shifted with every migration wave. A complete DR design drawn up at the start would have been obsolete before the estate finished landing.
Resilience in steps: deliver and prove active/passive early, then build to active/active once the migrated estate was in place.
Recovery architecture covered replication, workload priorities, network and storage dependencies, runbooks and recovery objectives. Backup capacity was remediated first so the recovery maths actually worked.
A Tier 0 recovery capability delivered to testing readiness, with runbooks, recovery objectives and an honest forward position.
Active/passive protection delivered and proven early. Active/active recorded at 85% at the last snapshot — handed over with the design and remaining work defined, not rounded up to done.
How it was run
Capacity before replication
Backup media-agent throughput, storage, concurrency and infrastructure constraints assessed and remediated to 100% — before recovery promises were made on top of them.
Catalogue hygiene
Backup catalogues pruned against retention policies, recovery requirements, compliance and data ownership — so restores find what they need, fast.
Workload priorities & objectives
Recovery architecture built around workload priorities, dependencies and recovery objectives — which systems come back first, and how fast, decided before the bad day.
Replication & dependencies
Replication design across network and storage dependencies into the recovery site, aligned to each migration wave as workloads landed.
Runbooks per priority workload
Recovery runbooks written and maintained as delivery artefacts — operational documents, not shelf-ware.
Prove it in steps
Active/passive delivered and proven first for real protection early; active/active built once the estate was in place. Waiting for the complete design would have left the site unprotected for longer.
The record
- Recovery site
- Cape Town colocation stood up as the group’s second site
- Active/passive resilience
- Delivered and proven early — real protection from the first step
- Active/active resilience
- Designed and progressed to 85% at the last recorded snapshot
- Recovery architecture
- Replication, workload priorities, dependencies, recovery objectives — to testing readiness
- Backup capacity
- Media-agent remediation at 100% — throughput, storage, concurrency
- Backup catalogues
- Pruned against retention, recovery, compliance and ownership
- Runbooks
- Recovery runbooks per priority workload, handed to operations
Decisions that shaped it
Steps, not a grand design. Active/passive first gave real protection early; active/active followed the migrated estate. The complete-design-first route would have left the new site exposed for longer.
Fix the backups first. Remediating media-agent capacity to 100% before building recovery promises on top — recovery objectives are physics, not paperwork.
Runbooks as deliverables. Operational readiness, runbooks and support handover were conditions of each wave — the DR capability landed in BAU hands, not in a project folder.
Report 85% as 85%. The active/active position was handed over at its recorded snapshot with the remaining work defined — no completion claimed beyond the record.
The three principles
“I had the pleasure of working with Karli Thebe on several key data centre projects. Karli consistently demonstrated exceptional focus and a strong drive towards achieving outcomes. Her ability to manage complex projects successfully is commendable, and she has proven to be a reliable and goal-oriented project manager.”
Hendrik van Graan · Senior Service Integration Manager · worked together, different companies · July 2025
Part of the Massmart national infrastructure programme (Apr 2023 — Apr 2025). Client individuals are referred to by role; backup, virtualisation and hardware products are described by category, not by name. No contract values or budgets are disclosed. Percentages are historical snapshots from the programme’s own record and are not restated as final acceptance.