Know before you move
Why it mattered
Three parts of the estate were obvious consolidation candidates and obvious risks to consolidate during a datacentre migration. File servers held years of departmental data with permissions nobody had reviewed. SharePoint had grown into several sites and farms with overlapping content. Remote Desktop Services hosted applications for users across the business on servers whose licensing and capacity were not well understood. Each could be rationalised; none could be rationalised safely while its underlying infrastructure was being moved.
The decision was to scope these as Phase 1 assessments — establish the facts, produce the consolidation options, and hand the client a decision-ready base without committing the engineers the migrations needed. Consolidation itself would follow in later phases, once the estate had settled in colocation. The mandate was delivery of the three assessments.
01 The Challenge
Ownership and permissions in file shares — establishing who owns what is slow and sensitive.
Departmental data accumulated over years has owners who have left and permissions that no longer match the organisation. And the temptation to fix things now was real: assessments uncover problems engineers want to solve immediately, and holding the scope to Phase 1 protected the migrations’ resources.
02 The Approach
Each assessment followed the same shape — inventory, fact-finding against a defined set of attributes, analysis of options, and handover to a named owner in the client’s organisation.
Content dependencies in SharePoint and licensing in Remote Desktop Services were established factually and handed over, not treated as findings to escalate.
03 The Outcome
Three Phase 1 assessments completed and handed to the client as decision-ready inputs — file servers, SharePoint and Remote Desktop Services.
Consolidation was deferred by design until after the datacentre migrations, protecting the programme’s critical path. Whether the client proceeded to consolidation afterwards is not known and is not claimed.
How it was run
File servers
Ownership, permissions, usage, duplication and retention assessed; consolidation and clean-up options produced.
SharePoint
Platform inventory, content-dependency map, supportability review and consolidation options.
Remote Desktop Services
Server inventory with usage, capacity, licensing and application dependencies, to inform a consolidation or modernisation decision.
Defined attributes
Each estate fact-found against a fixed set of attributes, so the assessment was finishable.
Handover to a named owner
Each assessment transferred to an identified owner in the client organisation.
The record
Decisions that shaped it
An assessment is a deliverable. Scoping these as Phase 1, with a defined output and owner, made them finishable and useful.
Do not consolidate during a migration. Consolidating user-facing estates while their infrastructure moved would have added risk with no migration benefit.
Ownership is the long pole. Establishing who owns data, sites and hosted applications took longer than any technical inventory.
Hand over to a name. Each assessment went to an identified owner — what gives a Phase 1 a chance of becoming a Phase 2.
The three principles
The client is Massmart; the engagement was an independent infrastructure project-management contract. Individuals are referred to by role. Permissions, licensing and data-retention detail established during the assessments is client-confidential and is not reproduced here. Platforms (SharePoint, Remote Desktop Services) are named as they appear in the public CV. Recorded status: Phase 1 complete. Full evidence register held in the KTH-Tech portfolio of evidence.